Which two steps of project team building are out of sequence?

A) You always identify skills before you identify people.
B) You always negotiate with the functional supervisor before you negotiate with top management.
C) You always negotiate with the functional supervisor before you talk to potential team members.
D) You always identify personnel before you talk to potential team members.


C

Business

You might also like to view...

Characteristics of the Likert scale include all of the following EXCEPT:

A) easy to construct. B) easy to administer. C) easy for the respondent to understand. D) the number of scale points can vary. E) respondents read a short phrase rather than an entire statement.

Business

What are four positive ways to promote diversity?

What will be an ideal response?

Business

Which of the following is an example of an event?

A. User interface B. Application logic C. Clicking a button on the screen D. Server-side processing

Business

A valid contract may be unenforceable for which reason(s)?

a. Failure to satisfy the statute of frauds. b. Running of the statute of limitations. c. Both failure to satisfy the statute of frauds and running of the statute of limitations. d. A valid contract is always enforceable.

Business