The earned value of a project is the

A. Total project cost to date.
B. Cost incurred minus the planned cost.
C. Percent of the original budget that has been earned by actual work.
D. Project cost to date adjusted for project scope changes.
E. Planned time-phased baseline of the value of work scheduled.


Answer: C

Business

You might also like to view...

According to Everett Rogers, which of the following types of customers are generally not interested in technology for its own sake, but are good at detecting the value of a new product and how it will enhance their lives?

A) innovators B) early adopters C) early majority D) late majority

Business

Identifying the most important information first then providing successive layers of support is referred to as what?

A) Linear organization B) Inverted pyramid C) Executive summary D) Micro rests E) Indirect approach

Business

Karl Lipton is the marketing communications coordinator for a major electronics manufacturer. He is assigned with charting out a communications strategy for a new range of mobile phones developed by his company

How will Karl's communications strategy look over the course of the mobile phones' life cycle?

Business

Why would a company create a knockoff of a product?

What will be an ideal response?

Business