The local soda machines union has some concerns regarding how busy these two machines are during the day. The union has work rules that demand that machines can be no busier than working two-thirds of their scheduled work shift
How many machines should they demand management add to the work force to bring them in line with the utilization rule?
A) 3 machines
B) 2 machines
C) 1 machine
D) none - they are already at that figure
Answer: C
You might also like to view...
The National Labor Relations Board (NLRB) is informed that Verdure Industries, a candle manufacturer, is violating a few labor laws of the United States. What steps should the NLRB take in this case?
What will be an ideal response?
A plant has four jobs to be assigned to four machines, and each machine has different manufacturing times for each product
The production manager wants to determine the optimal assignments of four jobs to four machines to minimize total manufacturing time. This problem can be most efficiently solved using the ________ model.
Pedregon Corporation has provided the following information: Cost per Unit Cost per PeriodDirect materials$6.35 Direct labor$3.75 Variable manufacturing overhead$1.50 Fixed manufacturing overhead $15,000Sales commissions$0.50 Variable administrative expense$0.55 Fixed selling and administrative expense $4,500If 4,000 units are sold, the total variable cost is closest to:
A. $50,600 B. $58,400 C. $46,400 D. $66,200
Union pension funds are prohibited from using their standing as stockholders to influence corporate strategies and governance.
Answer the following statement true (T) or false (F)