A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path

If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less?
A) -0.4
B) 0.0228
C) 0.3444
D) 0.9772
E) 4.2


B

Business

You might also like to view...

To be successful in a global workforce, managers need to have all of the following skills except:

A. engineering thinking skills B. human relations skills C. conceptual and design skills D. understanding of different cultures E. None of the above

Business

A posthumous heir can never inherit from a decedent

Indicate whether the statement is true or false

Business

Which model is used to describe the interaction of external forces that affect an organization's strategy and ability to compete?

A) network economics model B) competitive forces model C) competitive advantage model D) demand control model E) agency costs model

Business

When an employee is injured as a result of an employer's deliberate failure to provide a safe work-place, may the employee sue the employer for damages in a court of law?

Business