Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta

According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?
Job Sigma Delta
R 40 10
S 25 30
T 50 20
U 35 35
V 55 15

A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) R-V-T-S-U


C

Business

You might also like to view...

Price, distribution, and communication are the nonproduct elements that marketers modify to increase product sales

Indicate whether the statement is true or false

Business

Marketers find social news sites useful for promoting campaigns, creating conversations around related issues, and building Web site traffic

Indicate whether the statement is true or false a. True b. False

Business

A minor may disaffirm a contract only if the subject matter is illegal.

Answer the following statement true (T) or false (F)

Business

A company that enters a new business area in order to leverage existing expertise and achieve synergy across the newly combined set of products is following a ________ strategy.

A. international expansion B. related diversification C. unrelated diversification D. concentration on a single industry E. focused low-cost

Business