The project described by:

Activity Immediate
Predecessor Time
(days)
A -- 10
B A 4
C A 6
D B, C 7
E C 5

has a critical path of length of

A) 21 days.
B) 14 days.
C) 23 days.
D) 32 days.
E) None of the above


C

Business

You might also like to view...

Briefly describe the role of television as an advertising medium

What will be an ideal response?

Business

Section II of the practitioner’s model of human resource management includes the items that will allow the organization to get its work done successfully over long periods of time and is concerned with ______.

A. protecting and expanding B. staffing C. developing and managing D. compensating

Business

Which of the following accounts most likely would have an amount contained in the Income Statement columns of a work sheet but not in Balance Sheet columns of work sheet?

A) Office Supplies Expense B) Property Taxes Payable C) Retained Earnings D) Dividends

Business

When a customer feels uneasy about losing out on the benefits of a brand not purchased, she is likely to experience ________

A) selective retention B) selective attention C) selective distortion D) cognitive dissonance E) consumer ethnocentrism

Business