What is the expected completion time for the project?
Thai Construction
A construction firm from the Phuket Province of Thailand has a five activity project lined up for the coming month. They have had some difficulty getting firm estimates on the activity durations and have resorted to the three time estimates approach to plan the project. The activities and optimistic, most likely, and pessimistic estimates (in days) for each are shown in the table.
Activity Predecessor Optimistic Most Likely Pessimistic
A - 5 7 10
B - 11 15 18
C A 8 12 15
D - 9 11 12
E D 6 8 10
A) 14.83
B) 16.67
C) 18.83
D) 19.00
Answer: D
You might also like to view...
Which of the following is a disadvantage of PR?
A. It can misfire if mismanaged. B. It is subject to clutter. C. It does not contribute to sales. D. It is costly in both relative and absolute terms. E. It has less credibility than advertising.
Customized services ________
A) specialize in one or a few phases of the marketing research project B) are research studies conducted for different client firms but in a different way C) collect and sell common pools of data designed to serve information needs shared by a number of clients D) offer a wide variety of marketing research services tailored to suit a client's specific needs
The part of supply chain management that plans, implements, and controls the flow of goods, services, and information between the point of origin and the final customer is called
A. supply chain management. B. production management. C. logistics. D. value chain optimization. E. warehousing.
The ________ removed the last segments of Federal law that separated investment banking activities from commercial banking activities
A) Gramm-Leach-Bliley Act B) Sarbanes-Oxley Act C) Federal Deposit Insurance Corporation Improvement Act D) Glass-Steagall Act