Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at $10/hour) and that factory overhead would be $1,500,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,200,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate?

A. $6.67 per direct labor hour.
B. $7.08 per direct labor hour.
C. $8.33 per direct labor hour.
D. $6.00 per direct labor hour.
E. $7.50 per direct labor hour.


Answer: E

Business

You might also like to view...

Whereas ________ focus on what the product does, ________ focus on what the user experiences or gains

A) wants; needs B) selling points; benefits C) benefits; selling points D) actionable features; desirable benefits E) benefits; objections

Business

Cincy, Inc is building a $20 million dollar addition onto its distribution facility. To build the facility, Cincy must fill in two acres of wetlands. Under the Clean Water Act, Cincy must obtain a permit before filling in the wetlands

a. True b. False Indicate whether the statement is true or false

Business

Business strategy based upon technology leadership has advantages and disadvantages. List three examples of each.

What will be an ideal response?

Business

What is an example of a soft factor that influences expatriate performance?

a) Ability to establish relationships b) Generating profit c) Increasing market share d) All of the above.

Business