If a project has an expected completion time of 15 weeks with a variance of 4 weeks, the probability that the project will be completed in 12 weeks is ______.
A. about 6.7%
B. about 43.3%
C. about 29.1%
D. about 54.3%
A. about 6.7%
You might also like to view...
Avoiders may try to buy time or defuse strong emotions before handling con?ict
Indicate whether this statement is true or false.
The ________ sales presentation method is most appropriate when information needs to be gathered from the prospect, as is often the case in selling industrial products.
A. formula B. stimulus-response C. canned D. need-satisfaction E. persuasive
Which of the following is NOT a type of warranty under the UCC?
a. Express b. Fitness for a particular purpose c. Merchantability d. Specific performance
Finn gives his coin collection to Gert's Coin Shop to hold temporarily. While in the shop's possession, the collection is destroyed. Gert's may be liable for the loss if this was a bailment for
A. both parties' mutual benefit. B. Finn's sole benefit. C. Gert's sole benefit. D. neither party's benefit.