A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule

The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?
A) less than or equal to $5,000
B) greater than $5000 but less than or equal to $10,000
C) greater than $10,000 but less than or equal to $15,000
D) greater than $15,000


A

Business

You might also like to view...

Carter Company has a return on assets of 12% and a return on common stockholders' equity of 15%. What causes the difference in the two returns?

Business

When using the ________ ________ method, sales management first determines the segment's market potential and tallies the average number of sales calls needed to close each individual sale.

What will be an ideal response?

Business

The first unit produced in a process takes 480 hours. As the number of units produced doubles, production time decreases by 18%. Using the arithmetic approach, calculate the production time for the 64th unit.

a. 217 hours b. 146 hours c. 178 hours d. 156 hours

Business

A lockout amounts to a permanent closure of a plant to avoid unionization

Indicate whether the statement is true or false

Business