The simple moving average forecast _________.

a. Weights each period equally
b. Weights recent demand more lightly
c. Weights recent demand more heavily
d. Gives each period a weight of zero


a. Weights each period equally

Business

You might also like to view...

This question has two parts; be sure to answer both. First, explain McClelland's acquired needs theory. Second, discuss how you would use the model to motivate fellow students on a project team for one of your classes.

What will be an ideal response?

Business

Is it ethical to use neurological techniques to help develop leaders? Why not?

What will be an ideal response?

Business

When can research be justified, even if the financial risk of the decision is small?

a. The research can be done inexpensively b. It will not take very long to complete c. A lot of the information can be obtained from secondary sources d. It will help to clarify the actions to be take or decisions to be made e. all of the above

Business

The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery

The seven activities, their normal and expedited times (in days) and costs appear in the table. Just to be on the safe side, he decided to bring the project in at 53 days in case the delivery was a week early. Tell him what the least expensive 53-day project is; which activities should be reduced in duration, by how many days, and at the total cost, so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt, and get to work. Activity Normal time Crash time Normal Cost Crash Cost Predecessor A 5 3 500 1100 B 18 15 900 2300 A C 12 9 2500 3000 A D 9 7 500 650 B E 15 12 3000 5000 B F 12 10 4000 5000 C, D G 20 15 3600 4800 E, F

Business