The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000. The crash time for this activity is 3 weeks and is expected to cost $32,000. The cost slope for Activity X is calculated as ______.
a. (32,000 – 12,000) / (5 – 3)
b. (12,000 – 32,000) / (5 - 3)
c. (32,000 – 12,000) / (3 - 5)
d. (12,000 – 32,000) / (3 - 5)
a. (32,000 – 12,000) / (5 – 3)
You might also like to view...
Advertising allows the buyer to receive and compare the messages of various competitors
Indicate whether the statement is true or false
Governments are just about the only customers for certain products, such as jet fighters. The government is a(n) ________
A) end user B) organization C) gatekeeper D) facilitator E) reseller
What are some of the drawbacks of flexible working arrangements and what can be done to avoid them?
What will be an ideal response?
Ethnocentrism refers to the:
a. ability to appreciate the customs and cultures of others. b. study of the development of cultures. c. tendency to believe in the superiority of one's own culture. d. None of the answers are correct.