Different activities along the same path can have different total slack.
Answer the following statement true (T) or false (F)
True
If slack of one activity in a path is used, the ES for all activities that follow in the chain will be delayed and their slack reduced. Use of total slack must be coordinated with all participants in the activities that follow in the chain.
You might also like to view...
In a short essay, discuss the differences between a management decision problem and a marketing research problem
What will be an ideal response?
Which of the following is a key performance indicator of the internal business perspective of the balanced scorecard?
A) number of units produced per hour B) employee turnover C) cash flow D) number of cross-trained employees
Identify the necessary characteristics of accurate performance management tools.
What will be an ideal response?
Which line is represented by the equation 2X + Y ? 8?
A) BF B) CG C) DH D) AJ