Different activities along the same path can have different total slack.

Answer the following statement true (T) or false (F)


True

If slack of one activity in a path is used, the ES for all activities that follow in the chain will be delayed and their slack reduced. Use of total slack must be coordinated with all participants in the activities that follow in the chain.