If the total slack for a project is 4 days, this means

a. the activities on the path can be delayed a total of four days and the project still could be completed on time.
b. the activities on the path must be accelerated by four days for the project to be completed on time.
c. all the activities must be accelerated by four days for the project to be completed on time.
d. all the activities can be delayed by four days and the project still be completed on time.


a

Business

You might also like to view...

The difference between the principal amount of a note and its maturity value is called_____________

Fill in the blank(s) with correct word

Business

Which of the following is a disadvantage of using secondary data?

A) Secondary data is generally not appropriate for consumer products. B) Collecting secondary data is time consuming. C) Few sources exist for secondary data. D) Gathering secondary data is costly. E) Relevant secondary data can be difficult to locate.

Business

The manager of Center C is only responsible for generating and processing online orders of a large retailer. What type of responsibility center is Center C?

A) Discretionary cost center B) Profit center C) Revenue center D) Investment center

Business

During the close, attention should be focused on:

A) a more detailed analysis of customer objections B) the information gathered in the pre-approach stage C) the single benefit that generates the most excitement D) the ceremonial and visual aspects of the sales presentation E) the features the product has that set it apart from the competition

Business