Your most recent project performance report indicates that your cumulative Schedule Performance Index (SPI) is .85 and your cumulative Cost Performance Index (CPI) is .90 . What conclusions can you draw from these performance indices? What actions might you take to address project performance based on these results?


Key concepts to be covered in the response could include, but are not limited to:

The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ration of EV to PV. The SPI of .85 demonstrates that our project is proceeding less efficiently than planned and is behind schedule.

The cost performance index (CPI) is a measure of cost efficiency of budgeted resources, expressed as the ratio of EV to AC. The CPI of .90 demonstrates that our project is over budget, and that we are only receiving $0.90 worth of results for every dollar we have spent.

Given this information, we can also calculate the Estimate to Complete (ETC) and the Estimate at Completion (EAC), which are the expected cost needed to finish all the remaining project work, and the expected cost of completing all work.

Business

You might also like to view...

Individuals with high levels of cognitive involvement will display all of the following characteristics, except:

A) want more information prior to making a decision B) ask more questions during the purchase process C) spend less time deliberating prior to making a decision D) want clear message arguments

Business

Treating each customer seperately and giving the perception that he or she is being treated as a unique segment by delivering personalized products and services is known as:

A) selective marketing. B) mass marketing. C) sales orientation. D) mass customization.

Business

As a manager, George is flexible and adjusts to the needs of those around him even if those needs conflict with his own. It is likely that George has a(n) ______ self-schema.

Fill in the blank(s) with the appropriate word(s).

Business

Which of the following statements regarding accounting information systems is not true?

A. Accounting information systems communicate information to business decision makers. B. Accounting information systems collect and process data from transactions and events. C. Accounting information systems organize data in useful forms. D. Accounting information systems are not subject to internal control policies. E. Accounting information systems are useful to effective decision making.

Business