a. Which activities have float, and which activity costs the least on a per-day basis to speed up?
b. Are my most skilled resources available, and which activities are on the critical path?
c. Which activities are on the critical path, and which critical path activity costs the least on a per-day basis to speed up?
d. Which activities can I overlap by using time leads, and which work packages can I remove to reduce project scope?